Construction Methods and Measures for Water Treatment Structures and Equipment

Mar 08, 2026

Leave a message

1. Construction Process Flow
(1) Structures: Surveying and layout marking → Earthwork excavation → Concrete leveling layer → Rebar tying → Concrete pouring → Earthwork backfilling.
(2) Equipment Installation: Layout marking and positioning → Equipment foundation construction → Equipment placement → Leveling, alignment, and anchoring → Piping connections → Trial run.


2. Construction Methods for Structures
Upon completion of positioning and layout marking, the excavation of foundation pits for the structures must be carried out with appropriate side slopes in accordance with relevant specifications. During the rainy season, measures must be implemented to prevent rainwater from outside the pit from flowing in, and any rainwater accumulating within the pit must be drained promptly. If excavation extends below the groundwater table, open drainage ditches and sumps shall be established around the perimeter of the foundation pit. The bottom of the open ditches shall be 0.3m lower than the foundation base and constructed with a specific drainage gradient; the bottom of the sumps shall be 0.5m lower than the bottom of the drainage ditches. Groundwater will collect in the sumps via the drainage ditches and be pumped out of the pit using submersible pumps. Once excavation reaches the designed elevation, over-excavation or disturbance of the subgrade soil is strictly prohibited. A foundation pit inspection must be organized promptly, followed immediately by the execution of the next construction sequence, including the placement of the foundation leveling layer.
A dedicated shed for rebar processing shall be established at the construction site. Upon delivery to the site, rebar must undergo strict inspection in accordance with relevant national codes and standards; only after passing inspection may it be processed and utilized. Coiled rebar shall be straightened using the cold-drawing method. Rebar splices shall be executed via tying overlaps; the locations of these splices must strictly adhere to design requirements, or-in the absence of specific design requirements-must satisfy the requirements of national codes. To ensure the precise positioning of the rebar cage, layout lines shall be marked in advance; where necessary, welding methods may be employed to secure the rebar in place. For reinforced concrete foundation slabs, tank walls, beams, and floor slabs, cement mortar spacer blocks shall be used to control the thickness of the concrete cover (protective layer).
During formwork erection, particular attention must be paid to verifying the coordinates and quantities of all reserved openings and embedded parts; formwork erection may proceed only after these details have been verified as accurate by qualified technical personnel. Steel tubular scaffolding shall be utilized for formwork support and bracing. The timing for formwork removal shall be determined based on the compressive strength of concrete test cubes cured under site-specific conditions; removal may proceed only with the written consent of the project supervisor and upon receipt of a formal "Formwork Removal Notice" issued by the project's technical manager-arbitrary decisions regarding formwork removal are strictly prohibited. Concrete shall be mixed on-site; therefore, the quality of raw materials must be strictly controlled, the prescribed construction mix proportions accurately followed, and measurements strictly verified. Before pouring concrete, the elevations and structural axes must be re-verified; pouring may commence only after confirmation that all parameters are correct. The sequence of concrete pouring and the placement of construction joints must strictly comply with relevant code requirements. Construction joints shall undergo proper surface roughening treatment and be thoroughly cleaned and flushed prior to subsequent pouring. Prior to concrete pouring, records of concealed works inspections must be completed; construction may proceed only after these records have been signed and approved by the Supervising Engineer, and concrete test cubes must be prepared and retained in accordance with regulations. Concrete pouring operations must be continuous to prevent the formation of "cold joints." The concrete shall be thoroughly vibrated to ensure compaction, strictly preventing defects such as missed vibration, over-vibration, or formwork deformation. Upon completion of pouring, curing procedures shall be initiated promptly, adjusted according to ambient temperature conditions. No foot traffic, formwork installation, or scaffolding erection shall be permitted on the freshly poured concrete until its compressive strength has reached at least 1.2 N/mm².

Upon completion of the water treatment structures, a water-filling test shall be conducted. The filling process shall be executed in three stages, with each stage involving the addition of one-third of the structure's total capacity, allowing for an interval of no less than three hours between stages. After the tank has been filled to full capacity, it shall be observed for a period of 24 hours; if no leakage is detected, the structure is deemed to have passed the test.

 

3. Construction Methods for Water Treatment Equipment

Prior to equipment installation, the equipment model shall be verified to ensure it corresponds with the design specifications. Furthermore, the equipment shall be inspected-including its assembly and general condition-in accordance with the manufacturer's instructions, and detailed records of this inspection shall be maintained.

Based on the specified design elevations and the foundation requirements detailed in the equipment manufacturer's documentation, the installation layout shall be marked out and positioned on-site, and the equipment foundation shall be constructed accordingly. Once the strength of the foundation has reached the required specifications, the equipment shall be hoisted and set into its final position in a single operation.

 

4. Commissioning of Water Treatment Facilities

Upon the completion of the water treatment project, a comprehensive commissioning process must be undertaken to ensure that all performance indicators and technical parameters meet the specified design requirements. During the trial run and commissioning phase, representatives from the Supervision, Design, and End-User units shall participate jointly. Once the equipment has demonstrated compliance with design specifications-or has been optimized to its peak operational state-all participating parties shall sign off on the results, a formal commissioning report shall be compiled, and a certified monitoring report issued by an accredited monitoring agency shall be obtained.