(1) Holes are cut into the water distribution plate, and the water distributors are welded into place; alternatively, threaded connections may be selected to facilitate future replacement. Holes for the support legs are also cut.
(2) Branch pipes are welded to the bottom dished head; these serve primarily to support the water distribution plate.
(3) The branch pipes are passed through the water distribution plate and welded in place. The water distribution plate is then welded to the bottom dished head, requiring a double-sided weld.
(4) The main shell plate is rolled into a cylinder and welded to the bottom dished head.
(5) The top dished head is welded to the assembly.
(6) Openings are cut into the tank body: a top manhole (which may also serve as the packing loading port), a bottom manhole (positioned based on the clearance between the bottom dished head and the water distribution plate), a discharge port, a vent port, and inlet and outlet ports.
(7) The makeup water pipe and the threaded water distribution pipes are installed.
(8) The tank support legs and lifting lugs are welded to the tank body.
(9) The exterior surface undergoes mirror polishing and grinding.
(10) The external piping for the water circulation system is welded to the tank body.
(11) The inlet, drain, and outlet pipes are arranged in a "well-grid" configuration, utilizing five valves to regulate and distribute the water flow.